How much concrete for a 4×4 m slab at 125 mm thick?
You'll need about 2.1 m³ of concrete for this slab, including a 5% wastage allowance — that's roughly 195 × 20 kg premix bags if you're not ordering pre-mixed.
Over about 1.5 m³, pre-mixed delivery from a truck is usually cheaper and far less effort than mixing this many bags by hand — get a quote before defaulting to bags.
| Slab size | 4 m × 4 m |
|---|---|
| Thickness | 125 mm |
| Waste allowance | 5% |
| Concrete volume | 2.1 m³ |
| 20 kg bags | 195 |
| Approx. mass | 5.04 t (@ 2.4 t/m³) |
Assumptions
- 5% wastage allowance, the /site/materials calculator default.
- 20 kg premix bags yield about 0.0108 m³ each.
- Volume only — excludes reinforcement (mesh), formwork, base preparation and any fall/thickening at edges.
Check before you order: Confirm reinforcement (mesh/reo), site access for a mixer truck, and the exact thickness with your slab supplier or engineer before ordering — this figure is volume only.
How this is worked out & FAQ
How this is worked out
- Multiply length × width × thickness (in metres) for raw volume.
- Add the waste allowance.
- Divide by 0.0108 m³ per 20 kg bag and round up, if using bags.
FAQ
Should I order bags or a truck?
At this volume, a mixer truck is almost always cheaper and much less labour than bags — get a delivered quote before committing to bags.
Does this include reinforcement mesh?
No — this is concrete volume only. Use the Reo mesh calculator on /site/materials for SL-mesh sheet counts separately.
What about edge thickening or footings?
Not included — this assumes a uniform slab thickness. Add extra volume separately for any thickened edges or integrated footings.
Estimates only — allow for laps, cuts and site conditions. ← more concrete volume · All material calculators