How much concrete for a 3×6 m slab at 150 mm thick?

You'll need about 2.84 m³ of concrete for this slab, including a 5% wastage allowance — that's roughly 263 × 20 kg premix bags if you're not ordering pre-mixed.

Over about 1.5 m³, pre-mixed delivery from a truck is usually cheaper and far less effort than mixing this many bags by hand — get a quote before defaulting to bags.

Worked calculation
Slab size3 m × 6 m
Thickness150 mm
Waste allowance5%
Concrete volume2.84 m³
20 kg bags263
Approx. mass6.8 t (@ 2.4 t/m³)

Assumptions

Check before you order: Confirm reinforcement (mesh/reo), site access for a mixer truck, and the exact thickness with your slab supplier or engineer before ordering — this figure is volume only.

How this is worked out & FAQ

How this is worked out

  1. Multiply length × width × thickness (in metres) for raw volume.
  2. Add the waste allowance.
  3. Divide by 0.0108 m³ per 20 kg bag and round up, if using bags.

FAQ

Should I order bags or a truck?

At this volume, a mixer truck is almost always cheaper and much less labour than bags — get a delivered quote before committing to bags.

Does this include reinforcement mesh?

No — this is concrete volume only. Use the Reo mesh calculator on /site/materials for SL-mesh sheet counts separately.

What about edge thickening or footings?

Not included — this assumes a uniform slab thickness. Add extra volume separately for any thickened edges or integrated footings.

Estimates only — allow for laps, cuts and site conditions. ← more concrete volume · All material calculators